Location: Waynesville
Project owner: Waynesville R-VI School District
Contractor: KCI Construction, Lebanon
Estimated cost: $20.1 million
Estimated completion date: Fall 2003
This multilevel facility will comprise 242,614 square feet and will serve 1,800 high school students in grades nine through 12. The main entrance opens into a large commons area with a grand stair hall, a vaulted ceiling and a skylight.
The facility has more than 70 classrooms in the building with several computer and academic labs. The fine arts wing will house music, art and drama classrooms and a 20,000-square-foot auditorium that will seat 752 spectators. Other features include two gymnasiums, a mezzanine with an indoor walking track, an outdoor dining patio adjacent to the cafeteria and an 11,300-square-foot media center with an outdoor balcony.
Project work in Springfield corridor will continue into 2031.