Summer 2008 Project Profile: Cherokee Middle School
SBJ Staff
Posted online
General contractor: Flintco Inc.
Architect: Sapp Design Associates Architects PC
Engineers: Anderson Engineering Inc., civil; Scott Consulting Engineers PC, structural; and Malone Finkle Eckhardt & Collins Inc., mechanical, electrical and plumbing
Estimated cost: $15 million
The 110,000-square-foot addition and renovation project for Cherokee Middle School is on schedule despite recent weather, according to Flintco Project Manager Laurie Luna. She said crews were able to stay on pace by restructuring the work sequence. For example, she said, they focused on interior work earlier than anticipated. Completion is scheduled for fall 2009.
Complete with a 45-foot pedestrian bridge, this project adds a 10-foot-wide walking trail in front of Nixa’s High Pointe Elementary School and Summit Intermediate School.