Southwest Power Station Unit 2

Posted online
General contractors: Boldt Construction (Wisconsin), Cherne Contracting Corp. (Minnesota), Alberici Constructors Co. (St. Louis) and Sachs Electric Co. (Fenton)
Architect: Stanley Consultants (Iowa)
Engineer: Stanley Consultants
Estimated cost: $697.1 million

Crews are on pace to complete City Utilities second unit at the power station in late 2010, according to Joel Alexander, CU communications manager. The $697.1 million project is financed through 30-year bonds that customers will begin repaying in October, according to previous Springfield Business Journal coverage. The 94,000-square-foot, 300-megawatt facility will supplement CU’s existing power-generation capabilities, and emissions will be reduced through features such as air-pollution and mercury controls.[[In-content Ad]]

Comments

No comments on this story |
Please log in to add your comment
Editors' Pick
From the Ground Up: Sho-Me Fabrication LLC

Located in Partnership Industrial Center West, across the street from Vital Farms Inc. and Tank Components LLC, the new Sho-Me Fabrication building will include roughly 4,000 square feet of offices with more than 15,000 square feet of fabrication shop space, according to project officials.

Most Read
Update cookies preferences