YOUR BUSINESS AUTHORITY
Springfield, MO
Wastewater Treatment Plant expansion
Cost: $14.3 million
Funding: user fees and State Revolving Fund
Completion date: Fall 2001
General contractor: Branco Construction Co.
Engineer: Scott Consulting Engineers
School improvements
Cost: $6.4 million
Funding: General Obligation Bonds (citizens approved the sale of $7.2 million of general obligation bonds to build, furnish and repair school facilities; the bond money not used is being held for future improvements)
Completion dates: Range from September 2001 to December 2002
General contractor: Branco Construction Co.
Architect: Jack Ball & Associates
Park improvements
Cost: $5 million
Funding: Greene County Parks Tax and 1/2 cent Republic Capital Improvement Tax
Completion date: Summer 2003
General contractor: going to bid in May
Republic Police Station
Cost: $2.2 million
Funding: Greene County Law Enforcement Sales Tax
Completion date: April 9
General contractor: MECO Systems
Architect: Farnsworth Group Inc.
Road improvements (Miller Road and Lynne Street widening)
Cost: $2.2 million
Funding: 1/2 cent Transportation Sales Tax and 1/4 cent Storm Water Sales Tax Water Fund
Completion date: Miller Road June 2001; Lynne Street is still in planning stage
General contractor: Blevins Asphalt Construction Co.
Engineer: Scott Consulting Engineers
This installment of Springfield Business Journal’s Architects & Engineers Project Report showcases 26 endeavors by area design and engineering professionals.
Longtime employee sues Ozarks Tech, alleges retaliation
Cavender’s opens hat shop in southeast Springfield
Eric Schmitt introduces Modern Skies Act
Caterpillar to acquire John Fabick Tractor Co.
Springfield airport to cut the ribbon on $35M in construction projects
Legacy Bank accused in lawsuit of failing to protect customers in data breach