Project Profile: City Utilities Southwest Power Station Unit 2

Posted online


General contractors: Boldt Construction (Wisconsin), Cherne Contracting Corp. (Minnesota), Alberici Constructors Co. (St. Louis) and Sachs Electric Co. (Fenton)

Architect: Stanley Consultants (Iowa)

Engineers: Stanley Consultants

Estimated cost: $697.1 million

A team of 600 on-site workers is installing exterior siding and preparing to move work indoors at the City Utilities Southwest Power Station Unit 2. The $697.1 million project, financed through 30-year bonds, is still on track for completion in late 2010, said Joel Alexander, communications manager. With 94,000 square feet, the 300-megawatt plant is intended to supplement CU's other area plants and will use emissions-reducing technologies including air-pollution and mercury controls. It also will use treated municipal wastewater for cooling, according to www.cityutilities.net. Construction began in 2006. Customers will begin paying back the bonds through a rate increase in October 2010.[[In-content Ad]]

Comments

No comments on this story |
Please log in to add your comment
Editors' Pick
27North unveils new luxury off-road vehicles

Company also adds logistics, financial services to offerings.

Most Read
SBJ.net Poll
How do you feel about the city of Springfield's new elected leadership?

*

View results

Update cookies preferences