Following a six-month delay, the owner of the former Outland Complex in downtown Springfield said permits have been secured to remodel the space at 322 S. South Ave. into the Screaming Mary’s pub and dance club.
“We have been working with the city and the new tenants of our properties to ensure all city codes are met so our tenants can begin operating as soon as possible,” said Shawn Turner, owner of the real estate where the pub is set to open viaWV World Enterprises LLC, in an Aug. 5 email. “Our understanding is the permits were just approved and we will be moving forward. We are excited to bring more nightlife to downtown very soon.”
A commercial building permit to remodel the space was issued Aug. 5, according to the city of Springfield website. Turner did not respond to follow-up questions about the scope of remodel work needed and how long the project may take.
“The overall building permit has been issued, which means some work can commence,” said Martin Gugel, director of the city’s Building Development Services.
The project had been delayed for months. In early 2026, inspectors from the city of Springfield were on the property – 322, 324 and 326 S. South Ave. – after a complaint, Gugel said.
“Upon inspection, we noticed some of the remodel work that was going on, that was being done, and in some instances had been completed, without permit,” he said.
The city posted a warning notice on the property in mid-March, declaring the structures violated the city’s “dangerous, blighted and nuisance” building codes.
“There are three different addresses but essentially the same property,” he said.
Specifically, the city noted electrical systems, framing walls, plumbing and grease interceptor plumbing were installed without the required plans or permits.
As a result of the violation discovered, the structures were required to remain vacant until permits were secured to address or repair the affected areas so they comply with building codes.
Gugel said when work that requires a permit, such as framing or electrical upgrades, is done without a permit, the work itself can be “blighted” or a property maintenance code violation.
He said once a warning is posted on a building, the instructions pertain to the entire property, even if the issue that prompted the violation is isolated to a small area.
The posts on the doors of the building stated the structures must remain vacant until permits were secured to address or repair the issue and comply with building codes.
He said the legal wording on the post may appear severe, but unless occupation is prohibited, the owner – or individuals leasing the property from the owner – can still be on-site. However, they must get permits before any additional work is done.
“If it is dangerous, we skip straight to ‘Do not occupy,’” he said.
Gugel said the South Avenue property did not reach that threshold of concern. He said the city works with property owners, typically given them at least 30 days if not more, to pull the appropriate permits and start the work.
“We can extend that if we see progress is being made or, for whatever reason, it is just taking longer than expected,” he said.
Gugel said when it looks like progress has stalled, an administrative hearing can be scheduled and additional steps, including an order to repair an issue or board up a property, can be taken. A hearing for the 322 South Ave. property was set for September.
“We may cancel the hearing, that happens often, but we usually will wait until a little closer before we do that because we want to make sure that not only is progress happening, but it is being sustained,” he said.
Project work in Springfield corridor will continue into 2031.
Thanksgiving staple recalled at Costco
Warren Buffett donates $5.5B worth of Berkshire Hathaway shares
HBA of Greater Springfield executive officer to retire
Transportation officials discuss $471M Forward 44 initiative
Monday Morning Business Leads: Nov. 16, 2026
Former OMB Bank officer placed on probation
Letter to the Editor: No half-baked cake for our kids. No half-baked school grades, either.