Larry Snyder & Co. to build Carl Junction center

Posted online
Springfield-based general contractor Larry Snyder & Co. submitted a low bid of $3.84 million to build the Carl Junction Community Center.

Voters approved a $4.4 million bond issue in April 2007 to finance the 22,800-square-foot community center.

Steve Lawver, Carl Junction city administrator, said the winning bid includes four of the five alternate addendums that the city had requested from the architectural drawings, including a north canopy for Meals on Wheels and expanded parking.

Original estimates from the architectural renderings indicated that the project would cost more than $4.3 million, but Lawver said the bidding contractors found ways to save up to $500,000.

"It's been a very arduous process for the city and staff," said Kristi Beattie of Sapp Design Associates, which drew up the renderings for the project. "We had a very solid set of drawings that have been changed only slightly."

The community center will serve as a senior center, recreation center and city hall. It will feature a gym and indoor walking track, aerobics fitness rooms, and large meeting rooms for area organizations.

Carl Junction City Council plans to award a contract for construction at its Jan. 20 meeting. The project is scheduled to be complete by December.

Comments

No comments on this story |
Please log in to add your comment
Editors' Pick
Annual downtown holiday events combine for Nov. 21 celebration

Organizers hope to bolster client traffic to center city businesses.

Most Read
Update cookies preferences