YOUR BUSINESS AUTHORITY
Springfield, MO
General contractor: SPX Cooling Technologies (Overland Park, Kan.)
Architect: None
Engineers: SPX Cooling Technologies
Size: 128 feet long, 52 feet wide,
62 feet tall
Estimated cost: $3.5 million
Lender: None
Estimated completion date: May 31
Project description: City Utilities of Springfield is adding to its cooling tower, which cools lake water after the water is used to cool down electricity generators. The generators increase the water’s temperature by 5 F; the cooling tower brings it back down to lake temperature. Lonnie Killingsworth, power station manager, said construction started Jan. 20. The James River Power Station has been operational since 1957.
Contact Cory Smith with your From the Ground Up submissions. He may be reached by e-mail, by fax at (417) 799-0603 or by phone at (417) 831-3238.
Project work in Springfield corridor will continue into 2031.