Owner/developer: Northside Christian Church
General contractor: Walton Construction Co. LLC
Architect: Sapp Design Associates Architects PC
Engineers: Mettemeyer Engineering LLC, structural; Palmerton & Parrish Inc., civil; Malone Finkle Eckhardt & Collins Inc., mechanical, electrical and plumbing
Size: 40,000 square feet
Estimated cost: $5 million
Lender: Empire Bank
Estimated completion date: Sept. 1
Project description: Northside Christian Church is relocating to 41 acres it bought about five years ago. Established in 1973, the nondenominational church has been at 1311 E. Valley Water Mill Road for 31 years. The church hopes to sell its current 26,000-square-foot building, which sits on three acres, for a little more than $1 million. A listing agent hasn’t been selected yet, said Pastor Ed Holt. Northside Christian Church is paying for a $550,000 water main extension north along State Highway H, which Holt said would aid development in that area. He also said the church is going to reserve about 80 percent of its new campus for green space.
Reporter Cory Smith brings you new projects each week. He may be reached by e-mail at csmith@sbj.net, by fax at (417) 799-0603 or by phone at (417) 831-3238.
Organizers hope to bolster client traffic to center city businesses.
SBJ announces executive newsroom hires
Timeshare exit company owner sentenced for tax evasion
Trump, fast-food companies among targets of X redirects
Stockton district names next superintendent
State awards Springfield $4.6M for wastewater system improvements
Council modifies data center definitions bill, extends moratorium into next year