Owner/developer: Kay & Bernie LLC
General contractor: T&C Custom Homes Inc.
Architect: Brad Baker Architects PC
Engineers: Beatty Consulting Engineering, civil; Miller Engineering PC, structural; MEP Pond Creek Designs LLC, mechanical, electrical and plumbing
Size: 19,000 square feet
Estimated cost: $2 million
Lender: Springfield First Community Bank
Estimated completion date: May
Project description: The upper floor of the two-story, 19,000-square-foot Fremont Hills Dental Center will comprise an 18-operatory dental suite, said Mike Coffer, owner and president of general contractor T&C Custom Homes. Owner Dr. Bernard R. Tellez currently practices at 5349 N. 22nd St., Ste. 1, in Ozark. Coffer said the first-floor lease space can be divided into as many as three units, though no tenants had signed on yet. Coffer said the building has a modern lodge design and clerestory windows.

[[In-content Ad]]

Comments

No comments on this story |
Please log in to add your comment
Editors' Pick
Open for Business: CrossFit Republic

CrossFit Republic LLC changed ownership; Springfield nonprofit Care to Learn relocated; and the Fresh Gallery in downtown Springfield transitioned into a commercial venture.

Most Read
Update cookies preferences