City Utilities of Springfield has refinanced debt the utility provider took on through the 2006 construction of the second unit at John Twitty Energy Center.
New bonds were issued June 18 to replace 2006-issued bonds in the amount of $615 million, according to a news release. CU now owes $307 million and expects to pay off the debt in 2036.
CU officials expect the refinancing to save customers roughly $1.3 million annually.
CU received approval from both the Board of Public Utilities, the utility’s governing board, and Springfield City Council earlier this year to refinance the bonds.
"Due to market volatility this spring, City Utilities waited to finalize the timing of the issuance to ensure the best financial outcome," CU officials said in the release. "This refinancing effort is one of the many strategies City Utilities employs to ensure long-term affordability and value for its customers while continuing to provide safe, reliable services to the Springfield community."
John Twitty Energy Center, a 300-megawatt coal-fired plant, is located in southwest Springfield near the James River Freeway and Sunshine Street interchange.
A preengineered metal building to be used for the fabrication and installation of truck equipment is nearing completion in north Springfield, according to officials from Slone Architects & Interior Designers.
Clothing store closing Branson location
Ozarks Springbirds to take field in 2027
Nearly $53K in damages sought in excavation lawsuit
Simpson Strong-Tie breaks ground on $19M Missouri facility
Meadows at Wicklow cuts ribbon to meet housing need in Nixa
Springfield looks to define ‘data center’ and extend administrative delay on their development
How ironic that John Twitty made his name and his fortune by burning coal, but he now derives his livelihood from solar energy.