General contractor: Bailey Co. Architect: H Design Group Engineers: Colvin Jones Davis LLC, mechanical, electrical and plumbing; Anderson Engineering Inc., civil; and Pinnacle Design Consultants LLC, structural Estimated cost: $1.3 million, according to city building permit
CU Community Credit Union is remodeling its midtown location and adding nearly 4,500 square feet to its existing 7,732-square-foot building, said Jenny Reynolds, vice president of marketing. The project, which began in March, will update and expand the facility, which was last remodeled in 1995. The building will be extended to the south, and the lobby and drive-through teller lines will be joined. A tower element will be added, along with more parking and new signage. Interior design will be handled by Interior Planning Consultants Inc. and will include new paint, carpeting and furniture. Reynolds said the project is scheduled for completion by the end of 2010.[[In-content Ad]]