Construction in the Ozarks Spring 2010: City Utilities Southwest Power Station Unit 2
Posted online
General Contractors: Boldt Construction (Wisconsin), Cherne Contracting Corp. (Minnesota), Alberici Constructors Co. (St. Louis) and Sachs Electric Co. (Fenton) Architect: Stanley Consultants (Iowa) Engineers: Stanley Consultants Estimated Cost: $697.1 million Work on City Utilities’ $697.1 million second unit at Southwest Power Station is on pace for completion in late 2010, said Joel Alexander, CU communications manager. With 94,000 square feet, the 300-megawatt plant will supplement CU’s power-generating capabilities. It will include features such as air-pollution and mercury controls aimed at reducing emissions. The project, which requires about 600 workers on-site, is financed through 30-year bonds that customers will begin repaying in October, according to previous Springfield Business Journal coverage.[[In-content Ad]]