Construction in the Ozarks Spring 2010: City Utilities Southwest Power Station Unit 2

Posted online
General Contractors: Boldt Construction (Wisconsin), Cherne Contracting Corp. (Minnesota), Alberici Constructors Co. (St. Louis) and Sachs Electric Co. (Fenton)
Architect: Stanley Consultants (Iowa)
Engineers: Stanley Consultants
Estimated Cost: $697.1 million
Work on City Utilities’ $697.1 million second unit at Southwest Power Station is on pace for completion in late 2010, said Joel Alexander, CU communications manager. With 94,000 square feet, the 300-megawatt plant will supplement CU’s power-generating capabilities. It will include features such as air-pollution and mercury controls aimed at reducing emissions. The project, which requires about 600 workers on-site, is financed through 30-year bonds that customers will begin repaying in October, according to previous Springfield Business Journal coverage.

Comments

No comments on this story |
Please log in to add your comment
Editors' Pick
Annual downtown holiday events combine for Nov. 21 celebration

Organizers hope to bolster client traffic to center city businesses.

Most Read
SBJ.net Poll
How often do you use artificial intelligence for your business?

*

View results

Update cookies preferences