The caissons, or concrete supports, for the main chimney of the new plant have just been completed, and several other contracts have been awarded.
The contract for the 513-foot main chimney was awarded to Maryland-based Pullman Power. The structure – a reinforced concrete outer shell with carbon steel liner – should be complete by June 2009.
The turbine generator, which CU Associate General Manager for Electrical Supply Scott Miller called the “backbone of the plant,” will be built in Japan by Toshiba Corp. and delivered to the site by March 2009.
CU is also negotiating a contract for the main boiler island, which includes the coal silo, boiler and environmental protection equipment. That contract should be awarded this month.
With all the work at the site of the $697 million, 300-megawatt plant, CU officials say they will be updating the Southwest 2 Web site more frequently with information about building progress and contracts. The SW2 Web site is www.cityutilities.net/sw2/sw2.htm.
Nixa Superintendent Gearl Loden weighs in on A-F grade cards.
Thanksgiving staple recalled at Costco
HBA of Greater Springfield executive officer to retire
Warren Buffett donates $5.5B worth of Berkshire Hathaway shares
Transportation officials discuss $471M Forward 44 initiative
Letter to the Editor: No half-baked cake for our kids. No half-baked school grades, either.
Ozarks Farm Stop remains open after car crashes into building