Ask most small manufacturers how much inventory they carry, and you’ll usually get a dollar figure from the balance sheet. Ask the planner whether they trust the on-hand numbers in the system, and you’ll often get a pause.
That pause is expensive. When the people who buy and schedule parts don’t believe the system, they work around it. They pad orders just in case, walk the shelves before promising a customer a date, and pay to rush in parts that may already be in the building. None of that shows up as a line item called “bad inventory data,” but owners feel it in cash, overtime and missed ship dates.
Here’s what I’ve learned after 35 years about spotting the problem and fixing it without a big software project or large capital expenditure.
5 signs your numbers can’t be trusted
• Planners keep side spreadsheets. If the real answer lives in someone’s personal file, the system isn’t the system anymore.
• “Let me go look” is the standard answer. Every on-hand question needs a trip to the shelf.
• Expedite fees keep showing up. Rushing in parts you thought you had is a symptom, not bad luck.
• The year-end physical brings surprises. Big adjustments, up or down, mean errors piled up all year.
• Shelves are full, but lines still wait. Too much of the wrong stock and too little of the right stock usually travel together.
Why it happens in small plants
Small plants run lean. The same person may receive trucks, pull parts for the line and ship orders before lunch. Transactions get skipped or saved for later, and later turns into never. A short shipment gets received as complete. A scrapped part never gets recorded. An engineering change reaches the floor before it reaches the bill of material. Nobody did anything wrong, but every small gap pulls the system a little further from the shelf.
A 30-day reset
You don’t need a new enterprise resource planning system. You need a few habits and someone to own them.
• Week 1: Pick your critical parts. Choose the 20 to 30 items that stop a line or tie up the most dollars. They get your attention first.
• Week 2: Count them and record why. Compare each count to the system, and for every miss, write down the likely cause. Patterns show up fast.
• Week 3: Fix the biggest cause. If receiving is the leak, count at the dock before anything goes into the system. If it’s scrap, give the line a simple way to record it on the spot.
• Week 4: Make it routine. Set a weekly cycle count on those critical parts and review the misses with your team.
Put a name on it
The plants with accurate inventory aren’t the ones with the fanciest software. They’re the ones where someone owns the numbers and checks them every week. In a small shop, that might be the owner, a lead, or an outside adviser for a few hours a month.
What you get back
Numbers you can trust let you carry less safety stock, quote ship dates with confidence and stop paying premium freight for parts already on your shelves. Just as important, your team stops scrambling and starts planning.
If you do nothing else, start here: Next Monday, pick the 10 parts that matter most, count them and compare. What you find will tell you where to go next.
Scot Bruesewitz is the founder of Keystone Supply Chain Advisors, which provides fractional supply chain help to small and mid-size manufacturers in the area. He can be reached at scot@keystonesupplychainadvisors.com.
Advertising Plus Inc. recently acquired The Greek Corner Screen Printing and Embroidery.
Greater Springfield Area Sports Commission appoints executive director
Branson salon moves to Kimberling City
From The Ground Up: Brody’s Corner
KC's Country Club Plaza will get hefty incentive package
CJW Transportation Consultants acquired
Trump wants 10% cap on credit card interest rates
North Glenstone Community Improvement District names first executive director