Owner/developer: Nixa Public Schools
General contractor: DeWitt & Associates Inc.
Architect: Dake Wells Architecture Inc.
Engineers: Mettemeyer Engineering LLC, structural; Shaffer & Hines Inc., civil; and CJD Engineering LLC, mechanical, electrical and plumbing
Size: 3,200-seat stadium
Estimated cost: $5.8 million
Lender: None
Estimated completion: August
Project description: Construction at Nixa High School’s stadium will increase capacity to over 4,400 home team and visitor spectators, up from 2,500 fans, said Nixa Public Schools spokesperson Zac Rantz. The improvements are part of a $15 million bond issue passed by voters in 2019. Design plans call for a 3,200-seat stadium; a 10-room press box with restrooms and an elevator; visitor team bleachers; concession stands and restrooms, according to past Springfield Business Journal reporting. Nixa Public Schools this fall plans to hold sporting events with spectators at the stadium, said Rantz, adding the district has created multiple safety plans in response to the coronavirus pandemic.
Connected to Watkins Elementary School is a new storm shelter now under construction.
STL construction firm buys KC company
Updated: Systematic Savings Bank to be acquired in $14M deal
Webster University's deficit triples
Missouri House speaker accused of obstruction in ethics probe
‘Dress for your day’: Companies are relaxing dress codes amid evolving ideas about fashion
Developer targets opening by month's end for $10M apartment complex